Data indicate turbine operated normally before collapse

Jan 07, 2010 No Comments by

Data indicate turbine operated normally before collapse

Observer-Dispatch
Posted Jan 06, 2010 @ 07:46 PM
FENNER —
No unusual conditions were recorded in the internal computer of a 200-foot-tall turbine prior to its collapse last week at Fenner Wind Farm, officials said Wednesday.

Hank Sennott, a spokesman for Enel North America, the company that operates the wind farm, said analysis of data found in the turbine’s computer showed:

— The turbine had been operating normally before it crashed.

— The blades did not strike the turbine’s tower.

— The rotational speed of the blades was “reasonable” at the time of its collapse.

Those findings suggest that the accident did not occur under the same circumstances that caused another turbine to crash in March 2009 at the Noble Altona Windpark in Northern New York, Sennott said.

The crashes in Altona and Fenner both followed power outages and involved turbines manufactured by General Electric. However, Noble Enviornmental Power, the company that operates the Altona operation, said its turbine spun out of control due to a wiring anomaly.

“It’s not that situation at all,” Sennott said, who declined to discuss any other possible causes until an investigation is complete, which likely won’t be until the end of January.

The turbine that crashed at about 4 a.m. on Dec. 27 was one of 20 on the wind farm located northeast of Cazenovia. The wind farm has been in operation since 2001 and supplies enough electricity to serve at least 10,000 homes.

Articles, Wind

About the author

The author didnt add any Information to his profile yet
No Responses to “Data indicate turbine operated normally before collapse”

Leave a Reply

You must be logged in to post a comment.